Piping, mine equipment plan and construction of aluminum production plant from bauxite

The implementation of the project includes:
Implementation of about 1,000 tons of piping and related connections, including 13,000 inches of stress relief, 9,000 inches of radiography, as well as painting and insulation and hydrostatic testing for 720 lines.
How to procure materials: The employer was responsible for the procurement of materials and special equipment for the project.
Location of the project:

Jajarm-Khorasan

 